As of 1 p.m. today, Friday, Sept. 22, 2017, campfires are once again allowed in the Southeast Fire Centre. Burn barrels and all other forms of open burning remain restricted. The Town of Golden and Fire Chief Dave Balding would like to remind residents that although more seasonal weather conditions and...
More...

Pedestrian Bridge repairs continue this month

Sep 20, 2017
Beginning September 25th, work will resume on repairs to the Kicking Horse Pedestrian Bridge. Starting in early October, the bridge will close temporarily in order to undergo structural repairs. International Timber Frames Inc. and sub-contractor Jackson Contracting & Excavating spent the last few weeks of August building and installing the jacking pads that...
More...

Busy time of year for Town’s Operation Department

Sep 05, 2017
Fall is on its way and that means that the Town’s Operations Department is busy working to complete projects and get ready for the upcoming winter season.New Building Canada Fund Sewage Treatment Plant Upgrades: Beginning September 11, Phase 2 upgrades will start on the remaining two lagoons with substantial completion expected...
More...

The Golden Pool is closed for the season

Aug 31, 2017
ToG Rec Services staff would like to thank everyone for another great season at the Golden Pool! The pool is now closed for the season. The spray park will remain open until mid-September, so you can still take the littles to the park to cool off. Like many other communities in our...
More...

Update regarding wildfires in the Southeast Fire Centre

Aug 30, 2017
There are currently 46 active fires in the Southeast Fire Centre.  Please note that if there is any information that affects our area locally, we will certainly share it with residents on this page and through our other media channels.  The Town of Golden and the CSRD Area A have an integrated...
More...

Pedestrian Bridge repair update

Aug 24, 2017
UPDATE AUGUST 24, 2017: International Timber Frames Inc. and sub-contractor Jackson Contracting & Excavating are busy this week working to get the jacking pads built that will enable the lifting of the bridge to make repairs in late September.During this phase of construction, expected to be complete by August 31,...
More...

Update on Pedestrian Bridge repairs

Aug 23, 2017
UPDATE AUGUST 22, 2017: International Timber Frames Inc. and sub-contractor Jackson Contracting & Excavating are busy this week working to get the jacking pads built that will enable the lifting of the bridge to make repairs in late September. During this phase of construction, expected to be complete by August 31, 2017, the...
More...

2018 Proposed Permissive Tax Exemptions

Aug 22, 2017
In accordance with the notice requirements of Section 227 and the authority of Section 224 of the Community Charter, the following properties are proposed by bylaw, for permissive property taxation exemption for the 2018 calendar year. Also included are required estimates of exemption amounts for the following two years. Note that...
More...

Public notice regarding smoky sky advisories and wildfires

Aug 22, 2017
The Town of Golden will repost any information that pertains to the Southeast Fire Centre as it becomes available to us. In addition, if there is any information that affects our area locally, we will certainly share it with residents on this page and though our other media channels. At...
More...

Phase 1 repair work on the Pedestrian Bridge

Aug 21, 2017
Beginning this week, International Timber Frames Inc. and sub-contractor Jackson Contracting & Excavating will begin mobilizing materials to begin Phase 1 of the repairs to the Pedestrian Bridge.Phase 1 work involves the construction of in-stream jacking pads to be used for eventual lifting and support of the structure during repairs. This...
More...